The Reception site: footing pits, column formwork and set-out strings, with hills behind

Project details

  1. 01Consult
  2. 02Plan
  3. 03Build
  4. 04Control
  5. 05Deliver

The resort’s reception building, at foundation stage. The footings are in and the first columns are going up.

Location
Baan Ton Tan
Province
Nakhon Ratchasima
Service
Construction
Status
In progress
Stage
03 Build
Contractor
CON31 Prosper Group
A column cage with the set-out strings crossing over it
01Set-out
Looking down into a column cage inside its formwork
02Column cage
A concrete slump test: the slumped cone, the empty mould and a tape measure
03Slump test
A column stub standing in its footing pit
04Column stub
Footings and column stubs in the trench
05Footings
Column stubs standing in a row of footing trenches
06Footing trenches